THE MINISTER OF POWER ( SHRI ANANT G. GEETE )
(a) to (c) : A Statement is laid on the Table of the House.
STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF
STARRED QUESTION NO. 233 TO BE ANSWERED IN THE LOK SABHA ON
06.03.2003 REGARDING COST ESCALATION IN THE POWER PROJECTS.
(a) & (b) : Details of projects under execution which are
delayed are given in Annexe.
(c) : Two tier monitoring system has been evolved.
Central Electricity Authority (CEA) reviews the progress of
projects under implementation on a monthly basis. Secretary
(Power) conducts a similar review every quarter. Besides
for each project nodal officer has been designated in the
CEA who monitors the projects under his charge on day to day
basis with a view to facilitating resolutions of bottlenecks
through interactions with the concerned agencies at
appropriate levels.
ANNEXE REFERRED TO IN PARTS (a) & (b) OF THE STATEMENT LAID IN REPLY TO STARRED QUESTION
NO. 233 TO BE ANSWERED IN THE LOK SABHA ON 06.03.2003 REGARDING COST ESCALATION IN THE
POWER PROJECTS.
A. Thermal Power Projects (5
Name of State Capacity Comm.Sch. Estimated Remarks
project (MW) Original/ cost
Latest Latest/
Original (Rs. in crore)
Akrimota Gujarat 2x125 12/2002 1338.42/ Due to non-
Lignite 06/2003 1395.00 committal of funds
Based 03/2003 by IDBI. Project
Thermal 09/2003 authorities have
Power now approached
Plant, Power Finance
Unit-1&2, Corporation for funds.
Dabhol Maharashtra 1444 Uncertain 5604.00/ 95% works
Combined completed. 4 Gas
Cycle Gas Turbine already
Turbine synchronized. 1
Ph. II, Steam Turbine
Block rolled. Work held
I&II, up since 6/2001 due
to dispute between
Maharashtra State
Electricity Board
and DPC.
Neyveli Tamil 210 02/2001 1590.58/ The synchronization
Thermal Nadu 7/2003 1423.47# of unit is delayed
Power (For supply of critical
Station-1 unit 1 materials.
Expansion, & 2)
Unit-2,
B. Hydro Power Projects
Name State Capacity Comm. Estimated Reasons for Delay
of (MW) Sch. cost
Schem Original / Original/
latest Latest (Price
level) (Rs. crore)
Dhauligang Uttaranchal 280.00 1998-99 / 601.98 (12/89)/ Delay in tying up of
(NHPC) 2004-05 1578.31(8/99) funding, acquisition of land
and resettlement problems.
Dulhasti J&K 390.00 July,1994/ 1262.97(10/88) / Law and order problem,
(NHPC) Dec.,2003 3559.77(11/96) withdrawal of French
Consortium, poor geological
strata encountered in Head
Race Tunnel (Upstream) and
rock burst leading to burial
of Tunnel Boring Machine.
Purulia W.B. 900.00 2002-03/ 1456.56 (9/91) / Due to filing of Writ
PSS 2006-07 3188.90 (4/94) Petitions by the bidders and
consequential legal
impediment and also the
delay in diversion of forest
land for the Purulia Pumped
Storage Project, the
commencement of Lot-4-main
civil works was delayed.
Nathpa H.P. 1500.00 Dec.2001 to 1578.02 (12/88) / Landslide and need for rock
Jhakri March 2002/ 7666.31 (6/98) stabilisation work, flash
(NJPC) March, 2003 floods in July/Aug.2000,
to Dec., 2003 rock fall in desilting
chamber no 3&4 during
May,2000 and rock falls in
the desilting chamber no4
during Sept-Oct.2002 .
Tehri Uttaranchal 1000.00 1997-99/ 3391.40 (3/93) / Resettlement problems
St.I Dec.2004 5690.64 (8/99)
(THDC)
Larji H.P. 126.00 2002-03/ 796.98 (3/99) / Delay in award of contract
2004-05 908.64 (8/2001) packages.
Rock fall in Power House
area.
Sardar Guj/MP/ 1450.00 1994-96/ 1551.86 (1986-87) Resettlement problems,
Sarovar Mah. 2003- 07 / 3267.25 (1996-97) court cases and
withdrawal
of World Bank funding.
Bansagar M.P. 20.00 1996-97/ 51.06 (9/90) Funds constraints, delay in
Tons PH IV 2005-06 84.97 (2000) finalising the executing
agency and relief and
rehabilitation problems
Ghatghar Mah. 250.00 1995-96 / 485.96 (1992) / Delay in land acquisition
PSS 2004-05 1184.60 (1999-2000) and delay in award of major
works etc.
Srisailam A.P. 900.00 1993-95/ 418.00 (1985-86)/ 600 MW commissioned.
LBPH 2000-03 2620.00 (2001-02) Delay in award and slow
progress of civil works, etc.
Pykara T.N. 150.00 1994-95/ 70.16(1987-88)/ Delay in award of civil and
Ultimate 2003-04 373.06 (1998-99) mechanical works
Karbi Assam 100.00 1985-86/ 36.37 (1979) / Delayed due to frequent
Langpi 2004-05 470.86 changes in executing
(Lower agencies, fund constraints
Borpani)
Baspa H.P. 300.00 2001- 02/ 949.23 (12/93) / One unit successfully
St.II 2002-03 rotated on 24.1.2003.Delayed
under due to flash floods in
revision July/August,2000.
Maheshwar M.P. 400.00 2001-02/ 1569.27(1996- 97)/ Delayed due to withdrawal of
2005- 07 1673.00 (4/2000) foreign promoters of the
project developers. Fresh
financial closure required.